Scheduled Network Maintenance in TPE1 (Taipei)
Complete·Under maintenance·Oct 8, 9:00 AM - 6:00 PM
Wed, Oct 8, 2025, 06:00 PM
(2 months ago)
·
Affected components
TPE1 - Taipei (Chief LY)
Updates

Complete

Maintenance has completed

Wed, Oct 8, 2025, 06:00 PM

In progress

Maintenance has started

Wed, Oct 8, 2025, 09:00 AM(8 hours earlier)

Scheduled

During the maintenance window, we will increase the capacity of the link between us and the local transit provider from 10 Gbps to 100 Gbps. A brief reroute is expected, and the upgrade should take no longer than one hour. This should resolve the recent congestion issue.

Sun, Oct 5, 2025, 10:01 PM(2 days earlier)