The issue has been resolved. Due to operational constraints today, the planned work has been moved to tomorrow. Further details will be provided soon.
In progress
One hypervisor went offline due to a power connection issue. We are currently coordinating with the local technician on-site to inspect and restore the affected node. Further updates will be provided as more information becomes available.
In progress
Maintenance has started
Scheduled
We would like to inform you of scheduled maintenance affecting our services at the MOW1 PoP.
Date: 16 February 2026
Maintenance Window: 07:00 – 24:00 (Local Time)
Expected Impact: Up to 60 minutes of temporary performance degradation
This maintenance includes updates to our network infrastructure to optimize Internet performance and improve overall reliability.
We do not expect any connectivity outages during this period. However, you may experience brief slowdowns, potentially in up to two intervals of approximately 10 minutes each.
All services will continue operating and will return to normal automatically once the maintenance is complete. If you experience any issues beyond the expected impact, please contact our Support team via ticket or email.
Thank you for your understanding and cooperation.