Misaka Network, Inc.

Scheduled Network Maintenance in Asia (HKG12, NRT04, SIN03)
Complete·Under maintenance

The scheduled maintenance has been completed.

Tue, Sep 20, 2022, 08:17 PM
(2 years ago)
·
Affected components
SIN3 - Singapore (Equinix SG3)
NRT4 - Tokyo, Japan (Equinix TY8)
HKG12- Hong Kong (Equinix HK2)
Updates

Complete

The scheduled maintenance has been completed.

Tue, Sep 20, 2022, 08:17 PM

In progress

Verification is currently underway for the maintenance items.

Mon, Sep 19, 2022, 01:52 PM(1 day earlier)

In progress

Scheduled maintenance is still in progress. We will provide updates as necessary.

Mon, Sep 19, 2022, 12:17 PM(1 hour earlier)

In progress

Scheduled maintenance is currently in progress. We will provide updates as necessary.

Mon, Sep 19, 2022, 09:00 AM(3 hours earlier)

Scheduled

Maintenance will begin as scheduled in 60 minutes.

Mon, Sep 19, 2022, 08:00 AM(1 hour earlier)

Scheduled

We would like to announce planned network maintenance in our data centre in Hong Kong, Tokyo and Singapore, during which we will be working on major configuration changes on our core routers to allow for a stable throughput capacity. China optimized bandwidth would be unavailable during the maintenance and we would re-route to other carriers to ensure availability.

This maintenance will cause a connectivity outage of a maximum duration of 10 minutes during the maintenance window.

Wed, Sep 14, 2022, 12:16 AM(5 days earlier)
Powered by