Scheduled Power Maintenance in Taipei (TPE01)
Complete·Under maintenance

The maintenance has been rescheduled. We will inform you of the new date once we receive confirmation from the data center.

Mon, Nov 18, 2024, 07:28 AM
(7 months ago)
·
Affected components
TPE1 - Taipei (Chief LY)
Updates

Complete

The maintenance has been rescheduled. We will inform you of the new date once we receive confirmation from the data center.

Mon, Nov 18, 2024, 07:28 AM

In progress

Scheduled maintenance is currently in progress. We will provide updates as necessary.

Mon, Nov 18, 2024, 07:00 AM(28 minutes earlier)

Scheduled

The Taipei datacentre is undergoing power maintenance to ensure optimised power distribution.

We're expecting up to 60 minutes of power loss per circuit during the maintenance window, but no downtime is expected as all equipment has dual power supplies and we can confirm that they are in A/B redundant mode.

Mon, Nov 18, 2024, 06:47 AM(13 minutes earlier)