Misaka Network, Inc.

Scheduled Network Maintenance in Tokyo, JP (NRT04)
Complete·Under maintenance

The scheduled maintenance has been completed.

Sat, Oct 14, 2023, 11:00 AM
(1 year ago)
·
Affected components
NRT4 - Tokyo, Japan (Equinix TY8)
Updates

Complete

The scheduled maintenance has been completed.

Sat, Oct 14, 2023, 11:00 AM

In progress

Verification is currently underway for the maintenance items.

Sat, Oct 14, 2023, 10:16 AM(43 minutes earlier)

In progress

Scheduled maintenance is still in progress. We will provide updates as necessary.

Sat, Oct 14, 2023, 09:34 AM(42 minutes earlier)

In progress

Scheduled maintenance is currently in progress. We will provide updates as necessary.

Sat, Oct 14, 2023, 05:00 AM(4 hours earlier)

Scheduled

Maintenance will begin as scheduled in 60 minutes.

Sat, Oct 14, 2023, 04:00 AM(1 hour earlier)

Scheduled

We would like to announce a scheduled network maintenance in our data center at Equinix TY8, during which we will be moving the cross-connects to CDN77 and GSL to our new routers.

No connectivity outages are expected during the maintenance, as we have a redundant network design. However, you may notice a temporary increase in latency.

Date: Saturday, Oct 14, 2023Maintenance Window: 2:00 p.m. - 8:00 a.m. - Tokyo local timeOutage duration: maximum 10 minutesAffected server(s): ALL SERVERS

Sat, Oct 7, 2023, 07:56 AM(6 days earlier)