Misaka Network, Inc.

Site migration in EWR02 (Secaucus, NJ)
Complete·Under maintenance

The scheduled maintenance isn't completed yet.

Tue, Feb 23, 2021, 11:30 PM
(4 years ago)
·
Affected components
EWR2 - Secaucus, NJ, United States (Equinix NY2)
Updates

Complete

The scheduled maintenance isn't completed yet.

Tue, Feb 23, 2021, 11:30 PM

In progress

Onsite engineers are installing equipment in Equinix NY2. We will provide updates as necessary.

Tue, Feb 23, 2021, 11:29 PM

In progress

We've powered off our equipment and now removing them from vXchnge NJ-01.

Tue, Feb 23, 2021, 08:56 PM(2 hours earlier)

In progress

Scheduled maintenance is currently in progress. We will provide updates as necessary.

Tue, Feb 23, 2021, 07:30 PM(1 hour earlier)

Scheduled

We are currently working on expanding our Datacenter capacity in New York Metropolitan Area. We will be able to facilitate better connections and more servers in our new location in order to improve our current server fleet and improve the quality of our service.

To complete this expansion for this move we will be forced to move our servers to a new facility.We regret to announce that this will cause downtime for you as we will be fully moving to a new location. This process will take 2 hrs ~ 4 hrs.

Tue, Feb 23, 2021, 03:05 AM(16 hours earlier)
Powered by