Site migration in EWR02 (Secaucus, NJ)
Scheduled Maintenance Report for Misaka Network, Inc.
Completed
The scheduled maintenance isn't completed yet.
Posted Feb 23, 2021 - 23:30 UTC
Update
Onsite engineers are installing equipment in Equinix NY2. We will provide updates as necessary.
Posted Feb 23, 2021 - 23:29 UTC
Update
We've powered off our equipment and now removing them from vXchnge NJ-01.
Posted Feb 23, 2021 - 20:56 UTC
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Feb 23, 2021 - 19:30 UTC
Scheduled
We are currently working on expanding our Datacenter capacity in New York Metropolitan Area. We will be able to facilitate better connections and more servers in our new location in order to improve our current server fleet and improve the quality of our service.

To complete this expansion for this move we will be forced to move our servers to a new facility.
We regret to announce that this will cause downtime for you as we will be fully moving to a new location. This process will take 2 hrs ~ 4 hrs.
Posted Feb 23, 2021 - 03:05 UTC
This scheduled maintenance affected: Datacenters (Secaucus, NJ, United States - (EWR02)).